K&A Coal-to-Chemicals Platform: UCG / Ammonium Nitrate

Demonstration disclosure:

This is a pre-feasibility screening-level model intended to illustrate relative sensitivities and typical magnitudes, not a bankable feasibility study. Key caveats:

  1. All capex and opex factors are typical publicly available estimates, not vendor-quoted figures — client needs to benchmark against current EPC quotations before use.
  2. In the financial model, raw syngas composition and coal carbon content are treated as user inputs. The default syngas values are representative screening-level assumptions. Project-specific values should be established from the pilot plant studies and vendor-guaranteed performance.
  3. Coal gasification is a non-catalytic thermal process; catalyst and chemical costs reflect only downstream shift, AGR, and synthesis duty.
  4. No escalation is applied to prices or costs denominated in US dollars over the plant life; these remain in flat real terms. Prices and costs denominated in Indian rupees change in accordance with the exchange-rate depreciation assumption used in the model.
  5. The model is based on a standard UCG module producing 0.50 MMSCMD of raw syngas per module, together with its representative screening capital cost. The user may select an alternative UCG module capacity and cost from the available options based on discussions with the selected technology licensor.
K&A Suggestion for Subscribers
We suggest that clients who subscribe to our Platform first run the model using the K&A Base Case assumptions and review and record the complete set of results before changing any inputs. The Base Case provides a consistent reference point for understanding the model, the interaction between key assumptions and the resulting technical and financial outcomes. Clients can then challenge, refine or replace individual assumptions based on their own project experience, site-specific information, technology licensor inputs and other feasibility-stage assessments.

User Inputs

The entire input section is available for free viewing. An active subscription is required to run the model and access calculated results, sensitivity analysis and the K&A Strategic Perspective.

  1. Enter your subscription password (provided upon registration).




  2. Select the desired Ammonia plant capacity.
    Capacity selection should consider economies of scale, total capital commitment, downstream requirements, and whether Ammonia is produced for captive use or merchant sale. For an Ammonium Nitrate project, a typical plant capacity is around 2,000 TPD AN, for which approximately 920 TPD of installed Ammonia capacity is considered in this model. A substantially larger Ammonia plant, such as 3000 tpd or 5,000 TPD, would generally be unusual for a project of this AN scale unless significant merchant Ammonia production is also intended. The model therefore provides full flexibility to select any Ammonia plant capacity, while using 5,000 TPD as the default for this module.




  3. Ammonia Requirement for Ammonium Nitrate
    The integrated Ammonium Nitrate process involves two steps: Ammonia is first oxidised with oxygen from air to produce the intermediate Nitric Acid, which then reacts with additional Ammonia to form Ammonium Nitrate.
    NH3 + 2O2 → HNO3 + H2O
    NH3 + HNO3 → NH4NO3
    On a theoretical stoichiometric basis, the overall reaction requires 34/80 = 0.425 tonnes of Ammonia per tonne of Ammonium Nitrate. The model uses 0.46 tonnes of Ammonia per tonne of Ammonium Nitrate as the default practical requirement, reflecting the additional capacity required for real-world process conditions and operating margins. This corresponds to approximately 920 TPD of Ammonia for a 2,000 TPD Ammonium Nitrate plant. Users can modify this assumption where appropriate based on process design and technology guarantees.




  4. Percentage of Ammonia allocated to Ammonium Nitrate
    This model is an integrated Ammonia–Ammonium Nitrate model, with full flexibility to select any proportion of Ammonia production for Ammonium Nitrate production — from 0%, representing an Ammonia-only project with no Ammonium Nitrate plant, to 100%, representing a project in which all Ammonia production is allocated to the integrated Nitric Acid–Ammonium Nitrate chain.
    To illustrate this flexibility, the default Ammonium Nitrate production capacity is 2,000 TPD and the default installed Ammonia capacity is 5,000 TPD. The model therefore uses 18.4% as the default Ammonia-to-Ammonium Nitrate allocation.
    Clients can therefore evaluate different Ammonia plant capacities and different proportions of Ammonia allocated to Ammonium Nitrate, allowing the model to examine a wide range of integrated Ammonia–Ammonium Nitrate configurations.




  5. Realized Ammonia Price ($/t):
    Ammonia is a globally traded commodity and realized prices vary materially by region, market conditions, product specification and delivery basis. The model uses US$350/t as the default long-term screening assumption. Clients should replace this assumption with their own market outlook, applicable benchmark and expected realization where merchant Ammonia sales are contemplated.




  6. Realized Ammonium Nitrate Selling Price ($/t):
    Ammonium Nitrate is an internationally traded industrial product, with realized prices varying by region, market conditions, product grade, delivery basis and offtake arrangement. The model uses US$350/t as the default long-term screening assumption. This is intended as a screening assumption rather than a forecast of future international prices. Clients should replace this assumption with their own market outlook, applicable benchmark and expected realization for the target market and offtake arrangement. Nitric Acid is treated as an intermediate process step in this integrated Ammonia–Ammonium Nitrate model and is therefore not considered for merchant sale. Its production is internally linked to the Ammonia and Ammonium Nitrate process requirements.




  7. Underground unmineable coal price
    Default assumption: US$20/t, equivalent to approximately ₹1,900/t at an exchange rate of ₹95/US$. The price is expressed in US$ to provide an internationally benchmarkable basis. This is also relevant in the Indian context, as import coal prices form part of the National Coal Index methodology for certain grades of non-coking coal.




  8. Raw syngas composition — H2 (vol%)
    Raw syngas composition is a critical model assumption and should be validated with the UCG technology licensor. H₂ and CO composition, coal carbon content, coal grade, oxygen consumption and UCG operating conditions are interrelated and should therefore be assessed as an integrated set of assumptions.
    H2 concentration in raw syngas. The default assumption is 35 vol%.




  9. Raw syngas composition — CO (vol%)
    CO concentration in raw syngas. The default assumption is 30 vol%.




  10. Raw syngas composition — CO2 (vol%)
    Default composition: CO2 25% and CH4 + Others 10%, giving a total raw syngas composition of 100%.




  11. Raw syngas composition — CH4 and other minor components (vol%)
    Model check: Individual syngas components must sum to 100%.




  12. Carbon content of coal (fraction, dry basis)
    Carbon content of the underground coal (dry basis) is a principal driver of coal requirement. Indian non-mineable coal is typically considered to be having carbon content of 70% and that is our default assumption
    Carbon content should be assessed as part of the client's integrated coal-quality and syngas composition. The default assumption should be modified to reflect the project-specific coal assay.




  13. Carbon conversion efficiency — accounts for conversion efficiency of UCG
    Default assumption: 60%, based on published literature




  14. Government Coal Gasification Incentives
    While provision has been made to capture potential Capital incentives that could be offered by the Government of India the default model does not assume any such incentives. Clients can modify both the year and amount of each instalment based on their assessment of the incentives likely to be available to the project.
  15. Instalment Year Amount (₹ Crore)
    Instalment 1
    Instalment 2
    Instalment 3
    Instalment 4

  16. Availability of a single UCG Module
    Default: 100%. Final assumption should be established with the UCG technology licensor and based on the Client's operating expectations.





  17. Reference Single UCG Module production Capacity
    Single UCG Module syngas production capacity is a major project-design parameter. 0.5 MMSCMD per Module is used as the default.




  18. Reference single UCG Module Capital Cost
    Default assumption is US$10 million per Module producing 0.5 MMSCMD raw syngas




  19. Average UCG Module life
    Default assumption is 8 years


  20. Oxygen Requirement (ton per ton of Coal)
    Specific oxygen requirement is a key operating parameter and directly affects ASU capacity and capital cost. The default assumption is 0.50 tonnes of O2 per tonne of Coal. Actual consumption can vary materially with coal characteristics and operating conditions and should be validated with the selected licensor.




  21. Availability of a single ASU unit
    Accounts for planned maintenance and unplanned trips. Large-scale ASUs are a mature technology; the model uses a 95% default availability. The final assumption should be assessed with the selected ASU supplier and aligned with the overall plant operating philosophy.




  22. Reference ASU Capacity
    Reference ASU capacity is used for scaling ASU capital cost. The model uses 3,000 TPD of oxygen as the default reference capacity, broadly representative of a large-scale single-train ASU. Actual configuration and capacity should be determined from the project's oxygen requirement and selected supplier's design.




  23. Reference ASU ISBL Capital Cost
    Default assumption is US$90 million for a 3,000 TPD ASU, equivalent to approximately US$30,000 per TPD of oxygen capacity. Actual cost should be assessed with the selected ASU supplier and EPC contractor based on the required scope and project conditions.




  24. Reference AGR Capacity
    Acid Gas Removal (AGR) capacity can be expressed in Nm³/hr, Nm³/day, tonnes/hr or TPD. Because syngas composition affects conversion between volume and mass, the model expresses the reference capacity in TPD for intuitive comparison. The model internally converts syngas composition and molecular weights to determine the corresponding kmoles/day and mass flow




  25. Reference AGR Capital Cost
    Our default capital cost for a 20,000 TPD shifted syngas AGR system is US$150 million, equivalent to approximately US$7,500 per daily tonne of raw syngas capacity
    Actual cost can vary materially with acid-gas composition, removal requirements, technology selection and project scope




  26. Reference Water Gas Shift Capacity
    Water Gas Shift (WGS) capacity is defined by the quantity of CO processed through the shift reaction, which converts CO to H₂ and CO₂. The required WGS capacity varies with the downstream product and the desired syngas composition. Capacity can be expressed in Nm³/hr, Nm³/day, tonnes/hr or TPD; the model expresses it as TPD of CO processed for intuitive comparison.
    Default reference capacity: 1,500 TPD of CO processed.




  27. Reference Water Gas Shift Capital Cost
    The default reference capital cost is US$30 million for a WGS system processing 1,500 TPD of CO, equivalent to approximately US$20,000 per daily tonne of CO processed. This reference cost is used to scale WGS capital cost with capacity; actual cost depends on conversion requirements, catalyst configuration, operating conditions and project scope.




  28. Reference Ammonia Plant Capacity
    5,000 TPD represents a world-scale Ammonia plant capacity and is used as the default reference capacity in the model.




  29. Reference Ammonia ISBL Capital Cost
    The default reference Ammonia ISBL capital cost is US$400 million for a 5,000 TPD ammonia plant, covering the ammonia synthesis loop, compression, refrigeration, ammonia separation and associated equipment within the battery limits. Actual cost should be assessed with the selected technology licensor/EPC contractor and project-specific scope.




  30. Reference Nitric Acid Plant Capacity
    A 1,650 TPD Nitric Acid plant is used as the default reference capacity for the model, corresponding to a 2,000 TPD Ammonium Nitrate plant on the reference configuration. The capacity is expressed on a 100% HNO3-equivalent basis for simplicity and consistent capacity scaling. Actual plant capacity should be assessed with the selected technology licensor/EPC contractor.




  31. Reference Ammonium Nitrate Plant Capacity
    A 2,000 TPD Ammonium Nitrate (AN) plant is used as the default reference capacity for the model and represents a typical large commercial-scale configuration. The corresponding integrated Ammonia requirement is approximately 920 TPD, including the Ammonia required to produce the intermediate Nitric Acid. Actual plant capacity should be assessed based on project requirements, market/offtake considerations and the selected technology licensor/EPC contractor.




  32. Reference Nitric Acid ISBL Capital Cost
    The default reference Nitric Acid ISBL capital cost is US$70 million for a 1,650 TPD Nitric Acid plant, defined on a 100% HNO3-equivalent basis. The cost covers the Nitric Acid production section within the battery limits. Ammonia supply, utilities and other separately modelled upstream/OSBL facilities are excluded. Actual cost should be assessed with the selected technology licensor/EPC contractor and project-specific scope.




  33. Reference Ammonium Nitrate ISBL Capital Cost
    The default reference Ammonium Nitrate (AN) ISBL capital cost is US$100 million for a 2,000 TPD AN plant, covering the AN neutralisation, concentration and product finishing sections within the battery limits. Ammonia and Nitric Acid supply facilities, utilities and other separately modelled upstream/OSBL facilities are excluded. Actual cost should be assessed with the selected technology licensor/EPC contractor and project-specific scope.




  34. OSBL (% of ISBL Capital Cost)
    Outside Battery Limits (OSBL) includes infrastructure and facilities outside the main process-unit boundaries. OSBL cost can vary materially with site conditions, existing infrastructure and project scope, and may range from approximately 25% to 100% of ISBL cost. The model uses 40% of ISBL as the default screening assumption




  35. EPC (% of ISBL+OSBL Capital Cost)
    Engineering, Procurement and Construction (EPC) costs can vary with project size, complexity and contracting strategy; the model uses 15% of combined ISBL + OSBL cost as the default screening assumption




  36. Owners' Cost (% of ISBL+OSBL+EPC Capital Cost)
    Owners' costs include project-specific costs incurred by the owner outside the ISBL, OSBL and EPC scope. The model uses 10% of combined ISBL + OSBL + EPC cost as the default screening assumption; actual requirements depend on project structure, ownership arrangements and scope allocation.




  37. AGR Plant Scaling Exponent (Default = 0.6)




  38. WGS Plant Scaling Exponent (Default = 0.6)




  39. Ammonia Plant Scaling Exponent (Default = 0.6)




  40. Ammonium Nitrate Plant Scaling Exponent (Default = 0.6)




  41. Electricity Price
    Default assumption is US$70/MWh. Users should modify this to reflect the applicable project-specific electricity cost or power sourcing arrangement




  42. Ammonia Plant Power Consumption
    Default assumption is 150 kWh per tonne of Ammonia produced. Actual consumption should be assessed against the selected technology and project configuration




  43. Nitric Acid Plant Power Consumption
    Default assumption is 30 kWh per tonne of Nitric Acid produced, expressed on a 100% HNO3-equivalent basis. Actual electricity consumption should be assessed against the selected technology, plant configuration and heat-integration scheme.




  44. Ammonium Nitrate Plant Power Consumption
    Default assumption is 25 kWh per tonne of Ammonium Nitrate produced. Actual electricity consumption should be assessed against the selected technology, product finishing configuration and overall steam and heat-integration scheme.




  45. Ammonia Catalyst Consumption
    Default assumption is US$5/t of Ammonia. Actual catalyst consumption and replacement cost should be assessed with the selected technology/licensor.




  46. Nitric Acid Catalyst Consumption
    The Nitric Acid process uses platinum-rhodium catalyst gauze for ammonia oxidation. Catalyst consumption is relatively small and is influenced by catalyst loading, operating conditions, precious-metal losses and recovery arrangements. The model uses US$2/t of Nitric Acid as a provisional screening allowance for net catalyst-related consumption. Actual catalyst replacement, precious-metal loss and recovery costs should be assessed with the selected Nitric Acid technology licensor/EPC contractor.




  47. Plant utilization in first year of operation
    Year 1 utilization is assumed at 80%, increasing to 90% in Year 2 and 100% under normal operating conditions from Year 3 onward. These assumptions are considered reasonable ramp-up assumptions in conjunction with the separately specified equipment availability




  48. Plant utilization in second year of operation
    Year 1 utilization is assumed at 80%, increasing to 90% in Year 2 and 100% under normal operating conditions from Year 3 onward. These assumptions are considered reasonable ramp-up assumptions in conjunction with the separately specified equipment availability




  49. Plant Normal utilization
    The model assumes 100% utilization from the third operating year onward, subject to the separately specified availability assumptions. Given the default 75% individual gasifier availability, the 80% / 90% / 100% utilization profile is intended as a ramp-up and operating-utilization assumption and is not intended to imply 100% physical equipment availability




  50. Project construction period
    Integrated gasification and downstream chemical projects are technically complex and involve multiple major process units and interfaces. The model uses 4 years as the default construction period, while allowing users to test construction periods from 2 to 7 years. The appropriate period should ultimately be established from the project execution schedule, technology/licensor requirements and EPC strategy




  51. Total operating life of the project.
    The total operating life assumed for the project after commercial operation. The model uses 25 years as the default for project financial evaluation




  52. Depreciation (in Years)
    The period over which the depreciable project investment is depreciated for financial modelling purposes. The model uses 20 years as the default.




  53. UCG Sustaining CAPEX and Depreciation
    UCG modules are assumed to have a shorter economic life than the main surface project assets and therefore require periodic replacement. The model treats these module replacements as sustaining CAPEX, capitalises them as fixed assets, and depreciates each replacement over the assumed UCG Module Depreciation Period. The annual sustaining CAPEX is derived from the assumed UCG module requirement and module life, rather than being treated as a simple operating expense. This recurring replacement requirement is incorporated into the project's cash flow, depreciation, financial statements and fixed-asset schedule.
    The model uses 8 years as the default.




  54. Annual fixed operating cost.
    Represents recurring fixed operating and maintenance costs that do not vary directly with production volume. The model assumes 2.5% of applicable project CAPEX per year as the default




  55. Project discount rate
    The discount rate used to calculate the present value of project cash flows and Project NPV. The model uses 10% as the default screening assumption. The appropriate rate should reflect the project's risk profile, financing structure, currency and investor return requirements and should be assessed by the Client for detailed investment evaluation.




  56. Equity discount rate
    The discount rate used exclusively to calculate the present value of post-tax equity cash flows and Equity NPV. This represents the shareholders' required rate of return. The model uses 14% as the default screening assumption, while the Project Discount Rate continues to be used for Project NPV. Clients may modify this assumption to reflect project-specific investor hurdle rates.




  57. Debt portion of project financing
    The percentage of project cost assumed to be financed through debt. The model uses 70% debt financing as the default, with the balance funded through equity




  58. Interest rate on US Dollar debt
    The annual interest rate assumed on US Dollar-denominated project debt. The default assumption is 7%.



  59. Working Capital as a percentage of Sales
    The default assumption is 10%.



  60. Interest rate on Working Capital
    The annual interest rate assumed on Working Capital. The default assumption is 6%.



  61. Rupee debt interest rate spread over US Dollar debt
    The additional interest rate assumed for Rupee-denominated debt relative to the US Dollar debt rate. The default spread is 3 percentage points.




  62. Rupee / US Dollar Exchange Rate for 1st Year
    The exchange rate assumed for Project Year 1, which is the first year of the construction period. The model uses ₹95/US$ as the default assumption.



  63. Annual Rupee Depreciation
    The assumed annual depreciation of the Rupee against the US Dollar over the project period. The model uses 3% per year as the default assumption, applied from the Year 1 exchange-rate base.



  64. Tenor of debt repayment
    The period over which project debt principal is repaid following commercial operation. The model assumes a 12-year repayment tenor as the default




  65. Corporate income tax rate
    The corporate income tax rate applied to taxable project/equity cash flows in the financial model. The default assumption is 25%.
    The model is intended for screening-level financial evaluation and does not optimise project-specific tax depreciation schedules, tax holidays, credits or other tax incentives. Clients should incorporate applicable tax provisions and project-specific incentives during detailed financial evaluation




  66. Sustaining Capital (pct of Project Cost)
    Annual capital expenditure assumed to maintain the plant and replace or refurbish equipment over its operating life. The model assumes 1.5% of project cost per year as the default





  67. Leading Global Technology Suppliers

    The following companies are among the leading global technology licensors for the product pathways covered by the K&A Coal-to-Chemicals Platform. Companies are listed in alphabetical order. The listing is indicative and does not constitute a recommendation, ranking or endorsement by Karandikars & Associates.

    ProductLeading Technology Suppliers
    GasificationAir Liquide Engineering & Construction (Lurgi), ECUST, Shell
    Syngas Gas Cleaning & Water Gas ShiftBASF, Johnson Matthey, Topsoe
    Acetic AcidBP Cativa, Celanese, Eastman
    AmmoniaCasale, KBR, Topsoe, thyssenkrupp Uhde
    Ammonium NitrateCasale, Incro, thyssenkrupp Uhde
    Ammonium SulphateCasale, Technip Energies, thyssenkrupp Uhde
    ChloromethanesKureha, Shin-Etsu, Tokuyama
    Dimethyl Ether (DME)Johnson Matthey, Topsoe
    Ethanol (Methanol Route)DICP, ECUST
    Fischer-Tropsch (FT)Johnson Matthey, Sasol, Shell, Topsoe
    FormaldehydeJohnson Matthey FORMOX, Mitsubishi Gas Chemical, Topsoe
    MethanolCasale, Johnson Matthey, Topsoe
    Methanol-to-Olefins (MTO)DICP, Honeywell UOP
    MMA (ALPHA Route)Lucite International
    MMA (C4 Route)Mitsubishi Chemical, Röhm
    MTBECDTECH (Lummus), Honeywell UOP
    Sustainable Aviation Fuel (SAF)Axens, Honeywell UOP, Johnson Matthey, Topsoe
    Synthetic Natural Gas (SNG)Honeywell UOP (TREMP), Johnson Matthey, Topsoe
    TAMECDTECH (Lummus), Honeywell UOP
    UreaCasale, Saipem, Stamicarbon, Toyo Engineering

    Disclaimer: Technology licensors listed above are trademarks of their respective owners. Karandikars & Associates is an independent techno-economic advisory platform and is not affiliated with or endorsed by any listed company.