1720 MW Kamala Hydro Electric Project
CCEA has approved investment of Rs.26,069.50 crore for construction of Kamala Hydro Electric Project (HEP) in Kamle, Kra Daadi & Kurung Kumey Districts of Arunachal Pradesh. The estimated completion period for the project is 96 months
The project with an installed capacity of 1720 MW (8 x 210 MW & 1 x 40 MW) is expected to generate 6870 MU of energy. The power generated from the Project will strengthen power supply position in the state of Arunachal Pradesh, support in peak demand management, contribute to national grid balancing and will provide flood moderation benefit in the Brahmaputra valley. In addition to Kamala HEP, other hydropower projects—Subansiri Lower (2000 MW), Dibang Multipurpose (2880 MW) is under construction, and Etalin (3097 MW) is planned for development by NHPC Limited in Arunachal Pradesh
The Kamala HEP will be implemented through a Joint Venture Company between NHPC Limited and the Govt. of Arunachal Pradesh. Government of India shall extend Rs.4743.98 crore as budgetary support towards flood moderation component and Rs.1340 crore as budgetary support for enabling infrastructure viz. construction of roads, bridges and associated transmission system besides Central Financial Assistance of Rs.750 crore towards the equity share of the State
The State will receive 12% free power and an additional 1% earmarked for the Local Area Development Fund (LADF), along with significant infrastructure development and socio-economic benefits for the region
There will be significant improvement in the infrastructure in Kamle, Kra Daadi & Kurung Kumey Districts of Arunachal Pradesh, including the development of around 196 kms of roads and bridges, for the project which shall be mostly available for local use. The district will also benefit from the construction of essential infrastructure such as hospitals, schools, marketplaces etc. to be financed from dedicated project funds of Rs.8 crore. Local populace shall also be benefitted from compensations, employment and CSR activities
1200 MW Kalai-II Hydro Electric Project
CCEA has approved investment of Rs.14,105.83 crore for construction of Kalai-II Hydro Electric Project (HEP) on Lohit river in Anjaw District of Arunachal Pradesh. The estimated completion period for the project is 78 months
The project with an installed capacity of 1200 MW (6 x 190 MW & 1 x 60 MW) is expected to generate 4852.95 MU of energy annually. As the first hydro project in the Lohit Basin, it will strengthen power supply in the State, support in peak demand management, and contribute to balancing the national grid
The Project will be implemented through a Joint Venture Company between THDC India Limited and the Govt. of Arunachal Pradesh. Government of India shall extend ₹599.88 crore as budgetary support for construction of roads, bridges and associated transmission line under enabling infrastructure besides Central Financial Assistance of ₹750 crore towards equity share of the State
The State will receive 12% free power and an additional 1% earmarked for the Local Area Development Fund (LADF), along with significant infrastructure development and socio-economic benefits for the region
There will be significant improvement in infrastructure in Namsai and Anjaw District of Arunachal Pradesh, including the development of around 29 kilometres of roads and bridges, for the project which shall be mostly available for local use. Local populace shall also be benefitted from many sorts of compensations, employment and CSR activities